CONSTRUCTION PROGRESS UPDATE IN OCTOBER 2023 SPEEDING UP THE CONSTRUCTION WORKS FOR COMPOUND AMENITIES
By the end of October 2023, the Masterise Homes® team and partners have kept the ID fit-out works running seamlessly at all 05 LUMIÈRE Boulevard towers, curating living space with the highest fit-out quality for residents.
Regarding the facade works, the Final layer of paint is ongoing (80%). Shophouses at the tower podium, workers are cladding marble stones for Levels 1 and 2.
At the same time, the landscape has speeded up the construction work, including Tiling, decking, soil placement, and planting preparation.
Let's have a look at the construction progress update of LUMIÈRE Boulevard in October.
The landscape's hardscape work is finished. Our partners are currently working on the softscape projects, which include Tiling, decking, preparing the soil for planting, and planting.
The spaceship swimming pool has Masterise Homes® mark. Furthermore, this pool's length exceeds both the Olympic pool requirement and the pools seen in neighboring residential projects in Grand Park mega-township.