Overcoming the pressure of time, the challenge of the weather, the working atmosphere is still enthusiastic on the Masteri West Heights project site. All for one goal to be able to deliver the key to the customer on time.


By the end of June 2023, Masteri West Heights continues to make great impressions. Each building has reached the final stage of completion, many internal facilities have been formed to make residents wait for the day to come home:


Building A: Finishing of wall painting to the 39th floor

Building B: Construction completed to the 39th floor

Building C: Finishing plastering work to the 34th floor

Building D: Construction of aluminium and glass up to the 36 floor

The utility system is gradually showing clearly: Rooftop Panorama swimming pool, floating garage, internal park...

Along with the fast construction progress, the quality of the work is also strictly controlled by the general contractor Delta and the supervision consultant Artelia.