UPDATE CONSTRUCTION PROGRESS – JUL/2023: CONTINUE TO COMPLETE THE INSIDE AND AMENITIES

Masteri Centre Point affirms its position as the most luxurious residential compound with the interior space being completed with the highest quality.

By the end of July, the elevator lobby and corridor have been "lighted up" with a lighting system according to “5-star” hotel standards, creating a luxurious and sophisticated space right from the entrance to the apartment for residents. In the meantime, the interiors of apartments are still being furnished to international standards.

Outside the 05 towers, Masteri Centre Point has completed the construction of aluminium frames (from level 4 to the top roof), has completed 100% of the glass installation, and has continued to install external stone cladding for the shophouse area at levels 1&2.

At the same time, several landscape works have been accomplished, such as constructing planter boxes, paving walks with granite, and installing mosaic tiles at the swimming pool, gradually forming high-class amenities.

Masterise Homes and the main contractors are continuing to closely monitor construction items to the most rigorous standards, providing a modern lifestyle and being ready to welcome residents in 2023. View the most recent photographs from Masteri Centre Point!

The 05 Masteri Centre Point towers have an outstanding appearance in the most attractive location in Grand Park.

The “5-star” elevator lobby with lighting

Classy space has "lighted up" from the entryway to Masteri Centre Point apartment

The interior of apartments is still completed with the best quality, fully furnished

View of internal amenities from the balcony of apartment, several items are being implemented: paving the walkway, mosaic tiles for swimming pools, tree planting...

Close-up of an apartment's window

Outside, the project has finished installing aluminum frames on the top roof

The main hall of Masteri Centre Point, with a height of 6m, is nearing completion.

The basement has been painted and decorated

The project is scheduled to be completed in 2023!