주요 콘텐츠로 건너뛰기
news18/10/2023

CONSTRUCTION PROGRESS UPDATE IN SEPTEMBER 2023 LIFT LOBBIES AND APARTMENT CORRIDORS INSIDE TOWERS ARE BEING COMPLETED

One of the remarkable progressing updates of LUMIÈRE Boulevard in September is that the lift lobbies and apartment corridors inside the towers have been completed, and the lights are lit up, making interior space more luxurious, like 5-star hotels. At the same time, the architectural works, including: Masonry works, Plastering works and waterproofing, and screed works, are reaching 100% of completion.

For the facade works, All Aluminum Frames and glass installation were completed for all towers. The final layer of paint is ongoing (70%).

Let's take a look at images of the construction progress update of LUMIÈRE Boulevard in September 2023.
 

Hình 01

By the end of September 2023, the architectural works, including Masonry works, Plastering works and waterproofing, and screed works, are reaching 100% of completion.
 

Hình 02

The final layer of paint is ongoing (70%) at 5 towers.
 

Hình 03

 

Hình 04

Lift lobbies with a size of 2.7m(W) are being completed in 5 towers. LUMIÈRE Boulevard lift car will be high-speed versions with two button panels, which is highly convenient for resident use.
 

Hình 05

 

Hình 06

The main doors of LUMIÈRE Boulevard apartments are fire-rated and equipped with the modern Hafele lock.
 

Hình  07

ID work inside the apartments is ongoing with strict QA/QC to bring the best quality for customers.

Hình 07

 

Hình 08

Thanks to its prime location, right in the heart of Grand Park township, LUMIÈRE Boulevard is extremely close to public amenities such as the International School, less than a 3-minute drive.