With a high sense of responsibility from the Masterise Homes® team and partners, the entire construction site at The Rivus is being implemented simultaneously, with many items completed according to schedule and to the highest quality.
Highlights until June 2024:
- 100% of all villas’ piling work has been completed
- 31 villas in the SAVA subdivision have completed 90% of the façade works.
- River Park (phase 1) has completed more than 60% of the hardscape works; Central Park has completed piling works and earthworks for the swimming pool.
- Marina works: lifting bridge piling works completed and abutment pier work in progress. Piling works of ship lock (water gate) are in progress.
Overall, The Rivus is being completed and changing its “appearance” daily, standing out in a unique and rare location, the future connectivity center of Ho Chi Minh City. Let’s take a look at some of the latest pictures of The Rivus.