vien
Location The Collections Branded
Residences
Facilities Gallery Contact Liên hệ
sns-chat Go to Top
18/12/2024

CONSTRUCTION PROGRESS UPDATE IN DECEMBER 2024:​
CONSTRUCTION PROGRESS ACCELERATES COMPLETION,
WITH THE UPCOMING COMPLETION OF AMENITIES AND INFRASTRUCTURE WORKS

Facebook Twitter Linkedin Link

CONSTRUCTION PROGRESS UPDATE IN DECEMBER 2024:​  <br>CONSTRUCTION PROGRESS ACCELERATES COMPLETION, <br>WITH THE UPCOMING COMPLETION OF AMENITIES AND INFRASTRUCTURE WORKS

As of December 2024, Masterise Homes® team and its partners have made significant progress in the entire construction of The Rivus with many tasks completed on schedule and to the highest quality standards.​

Highlights as of December 2024:​

  • 31 villas in the SAVA zone have completed 100% of the façade works.​
  • The remaining villas have completed 100% of the superstructure works.​
  • Lift bridge begins a test run in November and progressing on the last stage.​
  • Marina Works: these decking are being installed and progressing on site.​
  • Children Park has completed 100% hardscape and planting of trees (Phase 1 and Phase 2).​
  • Central Park has completed 85% of the hardscape structure works and planting of trees commenced on site.​
  • River Park has completed 100% hardscape Phase 1 and 85% hardscape Phase 2. Planting of trees commenced on site.​
  • Infrastructure Works: 1st Asphalt layer completed for all zones; 100% complete Granite paving & walkways at Zone 1 and progressing at Main gate, Zone 2-3.​
  • External infrastructure: 1st Asphalt layer completed from Phuoc Thien street to Gate 1 of The Rivus; Phuoc Thien street will be completed, with a synchronous infrastructure for the entire area at the end of January 2025.​

The construction site is advancing rapidly, with many items expected to be completed at the end of the year.​

Meanwhile, landscaping work, including green spaces and sidewalk installations is progressing steadily, to deliver a sustainable and luxurious living environment for future residents.​​

Let’s look at some of the latest pictures of The Rivus.​

All villas in the SAVA zone have fully completed the façade works, the Children Park is also 100% complete.
All villas in the SAVA zone have fully completed the façade works, the Children Park is also 100% complete.
Close-up of some villas of the SAVA zone with completed façade works & Asphalt works.​
Close-up of some villas of the SAVA zone with completed façade works & Asphalt works.​
Overview of some villas of the SAVA zone with completed façade works & Asphalt works.​
Overview of some villas of the SAVA zone with completed façade works & Asphalt works.​
Close-up of some villas of the SAVA zone have completed façade works​
Close-up of some villas of the SAVA zone have completed façade works​
The lift bridge is testing in November; marina works progressing synchronously across multiple areas.​
The lift bridge is testing in November; marina works progressing synchronously across multiple areas.​
The Main gate is completed 100% & Granite paving is processing.​
The Main gate is completed 100% & Granite paving is processing.​
Central Park has completed 85% of the hardscape structure works and planting of trees commenced on site.​
Central Park has completed 85% of the hardscape structure works and planting of trees commenced on site.​
River Park has completed 100% hardscape Phase 1 and 85% hardscape Phase 2. Planting of trees commenced on site.​
River Park has completed 100% hardscape Phase 1 and 85% hardscape Phase 2. Planting of trees commenced on site.​
1st Asphalt layer completed for all zones; progressing walkways & Granite paving at Main gate, Zone 2.​
1st Asphalt layer completed for all zones; progressing walkways & Granite paving at Main gate, Zone 2.​
1st Asphalt layer completed from Phuoc Thien street to Gate 1 of The Rivus; Phuoc Thien street will be completed, with a synchronous infrastructure for the entire area at the end of January 2025.​
1st Asphalt layer completed from Phuoc Thien street to Gate 1 of The Rivus; Phuoc Thien street will be completed, with a synchronous infrastructure for the entire area at the end of January 2025.​

A MEMBER OF MASTERISE GROUP
Website owner: MASTERISE GROUP JOINT STOCK COMPANY
Enterprise Registration Certificate No. 0304840018 eighteenth issued, on 12 May 2020 by the Business Registration Ho Chi Minh
Copyright ©2019 belongs to MASTERISE GROUP JOINT STOCK COMPANY

Disclaimer: Whilst every care has been taken to ensure accuracy in the preparation of the information contained herein, no warranties whatsoever are given or legal representation provided in respect thereon. The developer reserves the right to modify information of the development or any part thereof as may be approved or required by the relevant authorities.
The mark “THE RIVUS – GATED DESIGN VILLAS BY ELIE SAAB”, the ELIE SAAB and ELIE SAAB Home Collection are used solely by Masterise Homes® under a license from SIM Licensing Limited and its affiliates.