As the Lunar New Year approaches, the construction site of The Rivus Villa project is bustling even more. Masterise Homes® team and its partners have demonstrated exceptional dedication and professionalism by working tirelessly around the clock to ensure timely project completion as planned.
Highlights as of early January 2025:
- 31 villas in the SAVA zone have completed 100% of the façade works.
- The remaining villas have completed 90% of the superstructure works Phase 2 & over 70% Phase 3.
- Lift bridge continue to trial operation in December 2024 and has completed 90% of the project.
- Children Park has completed 100% hardscape and planting of trees (Phase 1 and Phase 2).
- Central Park has completed 90% of the hardscape structure works and planting of trees commenced on site.
- River Park: Hardscape works is 85% completed; planting of trees is 60% completed and progressing.
- Infrastructure Works 100% complete Granite paving & walkways at Zone 1 and Main gate and progressing at Phases 2 & 3.
- External infrastructure 1st Asphalt layer completed from Phuoc Thien street to Gate 1 of The Rivus; Phuoc Thien street will be completed, with a synchronous infrastructure for the entire area in March, 2025.
Parallel to the construction progress, meticulous attention is given to planting and maintaining greenery and flowers, providing a sustainable and luxurious living environment for future residents.