UPDATE CONSTRUCTION PROGRESS – AUG/2023: 🍃 THE LANDSCAPE STRUCTURE, AMENITIES AND INTERIOR OF 05 TOWERS ARE QUICKLY COMPLETED 🍃

Masteri Centre Point has finished 100% of the landscape structure and is fast developing internal amenities and plants while finishing the inside of the 05 towers.

Masteri Centre Point has finished 100% of the aluminum fins of all blocks and 100% of landscape structures such as tiling internal walkways, swimming pool tiles, planting box, and compound wall... by the end of August. Many trees and water surface spaces are increasingly generating green spaces.

The apartments' living spaces are still being finished and installed furniture. The aluminum frame outside the shophouse area on level 1&2 has been completed, and glass is being fitted.

Masterise Homes and the main contractors are continuing to closely monitor construction items to the most rigorous standards, providing a modern lifestyle and being ready to welcome residents in 2023. View the most recent photographs from Masteri Centre Point!

05 tòa tháp đã hoàn thành 100% phần alu viền, tạo nên diện mạo đẳng cấp của dự án

The 05 towers feature finished aluminum fins, giving them an elegant appearance.

The internal space of Masteri Center Point is extremely spacious

Part of Masteri Center Point's internal space

Không gian xanh và mặt nước đang dần hình thành

The green landscape and water surface are taking shape gradually

After the project's landscape structure was completed, the contractor crew painstakingly assessed each region.

The inside of the apartments is still being finished to the highest level and fully furnished.

Close-ups of various minor features demonstrating international class and quality, such as opulent door nameplates, Legrand doorbells, Hafele hinges and eyes…

From the outside, the project's hues and class stand out.

The excellent "front row" location of Masteri Centre Point in the heart of Grand Park