LUMIÈRE Riverside – CONSTRUCTION PROGRESS UPDATE – OCT 2022

With the responsibility and professionalism of a reputable international real estate developer, Masterise Homes® strives to keep the LUMIÈRE Riverside project on schedule.

- Superstructure works are progressing quickly: West Tower reached level 26 already following the project plan schedule. Level 20 is completed at East Tower and work is ongoing at level 21.

- Architectural works including installing brick walls, plastering works & waterproofing is ongoing at both towers.

- MEP 1st fix installations are ongoing and reached level 17 for West Tower and level 12 for the East Tower.

- Façade Installations are ongoing at levels 9, 10, 11 & 12 for West Tower, and started at level 9 in East Tower.