LUMIÈRE Riverside - CONSTRUCTION PROGRESS UPDATE – JAN 2023

Inspired by “Leafscape” architecture, LUMIÈRE Riverside is an aesthetic masterpiece within the idea of nature, mastering elements of light, space, greenery and luxury. 

With the close monitoring by the Project Management team and our main contractors, LUMIÈRE Riverside construction progress is on schedule and the hand-over is expected to go as planned.
 
Superstructure works is in progress:

+ Concrete cast for level 31 slab completed, rebar & formwork on going for level 32 at East tower; ongoing up to level 38 and level 39 for the West tower respectively.

+ LUMIÈRE Shops: Concrete cast for level 7 completed and at the same time, rebar & formwork started for the swimming pool technical floor. 

- Architectural works including masonry, internal plastering, water proofing & screed works is ongoing up to level 27 at East tower and level 32 at West tower.

- MEP 1st & 2nd fix installations for all systems is progressing up to level 28 for East tower and level 32 for the West tower.

- Façade works: external plastering is ongoing up to level 22, aluminum frames & glass installation is ongoing up to level 21 for East tower; ongoing up to level 28 and level 25 for the West tower respectively; installation of aluminum frames is ongoing for all the building elevations of
LUMIÈRE Shops.

- ID Fitout Works: suspended ceiling framing installations and 1st coat of paint application started at both towers in low levels.
 