Feb, 2023

CONSTRUCTION PROGRESS UPDATE – FEB 2023

With responsibility and professionalism of a reputable international real estate developer, Masterise Homes strives to keep the LUMIÈRE riverside project on schedule.

- Superstructure works is in progress: concrete cast for level 33 slab completed, rebar & formwork on going for level 34 at East tower; ongoing up to level 40 and level 41 for the West tower respectively.

- Architectural works including masonry, internal plastering, water proofing & screed works is ongoing up to level 29 at East tower and level 36 at West tower.

- MEP 1st & 2nd fix installations for all systems is progressing up to level 28 for East tower and level 34 for the West tower.

- Façade works: external plastering is ongoing up to level 22, aluminum frames & glass installation is ongoing up to level 23 for East tower; ongoing up to level 29 and level 26 for the West tower respectively; installation of aluminum frames is ongoing for all the building elevations of LUMIÈRE Shops.

- ID Fitout Works: suspended ceiling framing installations and 1st coat of paint application started at both towers in low levels.

Inspired by “Leafscape” architecture, LUMIÈRE riverside is an aesthetic masterpiece within the idea of nature, mastering elements of light, space, greenery and luxury.